1 / 5

LBT Q3 2007 Engineering Review

LBT Q3 2007 Engineering Review. HBSC Hydrostatic Bearing System. Highlights (Q3/2007). WinCC (engineering diagnostic) can log data All 8 lateral pads modified to reduce oil consumption, and installed. Open Issues. Technical PLC Control law unknown, undocumented.

jaguar
Download Presentation

LBT Q3 2007 Engineering Review

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. LBT Q3 2007 Engineering Review HBSC Hydrostatic Bearing System

  2. Highlights (Q3/2007) • WinCC (engineering diagnostic) can log data • All 8 lateral pads modified to reduce oil consumption, and installed LBT Q3 2007 Engineering Review

  3. Open Issues • Technical • PLC Control law unknown, undocumented. • Firewall not penetrable for WinCC • Capillaries not installed in El and Az pads • Capilaries uncharacterized/adjusted • Schedule • None • Financial • None • Resource • Mountain support pacing operation • Network and Firewall communications issues unresolved LBT Q3 2007 Engineering Review

  4. Progress (Q3/2007) • WinCC (engineering diagnostic) running and capable of datalogging • NRAO modified 7 pads in their shop across street • All modified lateral pads have been reinstalled • Capilaries installed on all 8 laterals, LBT Q3 2007 Engineering Review

  5. Planning (Q3/2007) • Move the El and Az capillaries to the pads and resize • Systematic measurement of lift, tuning system to maximize stiffness • Replace hoses with hard pipe on level 5 • Document existing S7 code with a process flowchart (VoltsDC) • Describe new control laws correcting: • pressure OK • system shutdown when pocket pressures fail • control around pressure, not lookup table (LBT) • Rewrite PLC code using new control laws (VoltsDC) • Reduce system pressure from 120 to 95 bar. LBT Q3 2007 Engineering Review