An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. LBT Q4 2007 Engineering Review DYB

  2. Highlights (Q4/2007) • Currently in Commissioning Phase • System is functioning and we are able to run the system with the MCS. • System senses swing arm configuration and performs the reconcile command and manual trim commands. • All hardware and electronics installed except bypass valves and insulation. • Bypass valves still need to be installed. • Pipe insulation work in progress • Final system and software tests are in progress. • Current Completion Date is February/March, 2008. Slip from Nov 30th due to scarcity of time on telescope. LBT Q4 2007 Engineering Review

  3. Open Issues • Technical • Installation of bypass valves and insulation, and final shake down of PLC software. • Schedule • Telescope time and impact on acceptance tests and any punchlist work. • Financial • None • Resource • Need ETS techs help to complete insulation due to competing priorities of mountain staff. • PLC Programmer’s time needed to complete debugging of software. LBT Q4 2007 Engineering Review

  4. Progress (Q4/2007) • Procurement • Bypass Valves, Level Sensors, Longer and Flowmeter Cable (Planned 2nd week Nov.) (Completed 1st week of Dec.) • Installation • Insulation (Planned Oct) (Slip to January dependant on ETS help) • Bypass Valves, Level Sensors, and vent lines through cable wrap (Planned Nov) Level sensors and vent lines completed in Dec. Bypass valves will be installed Dec 27th. • Commissioning • Software Tests (Planned Oct ) (Continuing into January) • Commission Level Sensors and Calibrate Overflow Sensors (Planned Nov) (Completed in November.) • Acceptance Tests and Handover (Planned Nov) (Now planned to complete acceptance tests in February/March) • Documentation (Planned Nov) (Complete in January) LBT Q4 2007 Engineering Review

  5. Progress Cont. (Q4/2007) Vent Lines in Drape Level sensor and support tube installed LBT Q4 2007 Engineering Review

  6. Planning (Q1/2008) • Installation • Complete Insulation (January) • Bypass Valves (Dec 27th) • Commissioning • Complete Software Tests (January) • Acceptance Tests and Handover (February/March) • Documentation (January) LBT Q4 2007 Engineering Review