LBT Q1 2007 Engineering Review ALPC – Primary Mirror Aluminum Shooting
Highlights (Q1/2007) • Got some documentation, in the form of a PowerPoint LBT Q1 2007 Engineering Review
Open Issues • Technical • Documentation for Aluminization System • Upgrade of Aluminization System • Cleaning/Stripping System • Schedule • Aluminizing to occur some time in July or August? • Financial • None • Resources • None LBT Q1 2007 Engineering Review
Progress (Q1/2007) • In addition to the Highlights • Bell Jar Stand Modification Design LBT Q1 2007 Engineering Review
Planning (Q2/2007) • Aluminizing in Q3 • Belljar Stand Modification LBT Q1 2007 Engineering Review
Belljar Stand Modification LBT Q1 2007 Engineering Review