60 likes | 188 Views
PSPI: PEPSI installation preparation, includes all of the pier modifications. LBT Q2 2007 Engineering Review. Highlights (Q2/2007). Install 47 deg coolant to PEPSI bridge location Install clean dry air to PEPSI bridge location Schedule PEPSI team, Frank and Emil visit first of July 2007.
E N D
PSPI: PEPSI installation preparation, includes all of the pier modifications LBT Q2 2007 Engineering Review
Highlights (Q2/2007) Install 47 deg coolant to PEPSI bridge location Install clean dry air to PEPSI bridge location Schedule PEPSI team, Frank and Emil visit first of July 2007
Open Issues Technical Definition of power at connection point Schedule Part scheduled Financial Cost of paint and materials Resource Identify paint and paint contractor
Progress (Q2/2007) Install 47 deg coolant to PEPSI bridge location Install clean dry air to PEPSI bridge location
Planning (Q3/2007) Terminate fibers Define and install the connection point box Install more services Move J box in pier up to 4 M, Q3 2007 Move florescence lights in pier up to 4 M, Q3 2007 Installing energy chain/ cable chain Installing AZ hole support structure Installing gallery brackets
Planning (before 2008) Install services install E-net, install E-stop install telephone install power and conduit Insulate all pipe carrying liquids Epoxy paint entire floor Paint walls with epoxy paint