Monthly RCM Report for February 2008 David Thresher Frank Blankinship
Agenda • Buildings Covered: 2168, 2169 • Run to Fail items • MAS changes • Equipment Add ons • RCM team concerns
Run to Fail by Facility • 2168: 327 Items • Annualized MHRS: 368.3 • Replacement Cost: $10,531.50 • 2169: 168 Items • Annualized MHRS: 240.59 • Replacement Cost: $13,379.00 • TOTAL MHRS = 608.86 annually • TOTAL Savings = $23,910.50 annually
Recommended MAS Changes by Facility 01/24/08 to 2/25/08 • Building 2168: 13 items • Savings of 10.92 MHRS • Building 2169: 45 items • Savings of 571.53 MHRS Total savings 582.45 MHRS = $29,122.5 annually
Equipment Add Items • Equipment to be added on since 9/1/07 • Total of 91 items • Total MHRS = 200.99 annually
Concerns • Priorities • Man Power • Supply System • Shop Cooperation • Training • Government Approval • Perception
Summary • Facilities Reviewed = 4 • Total Items Condition Assessed = 619 • Total Proposed MHRS Saved = 529.3 • Total Proposed Savings = $84,664