1 / 6

Monthly RCM Report January

Monthly RCM Report January. David Thresher Frank Blankinship. Agenda. Run to Fail items MAS changes Bar Codes Applied MAS Example RCM team concerns. Run to Fail by Date. 24 Items 12/14/07-01/24/08 Annualized MHRS: 47 Total MHRS = $2350 Replacement Cost: $131,330

almira
Download Presentation

Monthly RCM Report January

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Monthly RCM Report January David Thresher Frank Blankinship

  2. Agenda • Run to Fail items • MAS changes • Bar Codes Applied • MAS Example • RCM team concerns

  3. Run to Fail by Date • 24 Items 12/14/07-01/24/08 • Annualized MHRS: 47 • Total MHRS = $2350 • Replacement Cost: $131,330 • Total Run to Fail 10/15/07 -12/24/08 • 140 Items • Annualized MHRS: 118 • Total MHRS = $5900 • Replacement Cost: $243,890.00

  4. Recommended MAS Changes by Date • MAS Changes 12/14/07-01/24/08 • Savings 719 MHRS = $35,950 • Total MAS Changes 10/15/07-1/24/08 • Savings 760 MHRS = $38,000

  5. Bar Codes Applied to Date • 436 Bar Codes Applied

  6. Concerns • Priorities • Making MAS Changes • Loading IWIMS • Man Power • Shop Help • Government Meeting