An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. TCC2-TDC2 working groupHandling means for the TAX repairs 21th September 2011 JL GRENARD EN-HE

  2. Handling means for the TAX repairs • Simple rotative hook • Double rotative hooks • Modification of the crane • Vision system • Radiation measurement mobile platform • Standard transport means JL GRENARD EN-HE

  3. Simple rotative hook • Adaptation of the hook used for HiRadMat • Lifting capacity 4t • Will be operated with a remote control Production finished Need to be tested Mounting on the crane need some adaptations (installation of a cable Realer, and a power plug) JL GRENARD EN-HE

  4. Double rotative hooks • Two rotative hooks mounted on a motorized pivot • Lifting capacity 8t • Will be operated with a remote control Production and procurement started -> ready end of December Mounting on the crane need some adaptations (installation of a cable Realer, and a power plug) JL GRENARD EN-HE

  5. Modification of the crane • Installation of remote control • Installation of a cable realer for the supply and the control of the different ‘’handling tools’’ • Remote control ordered delivery by December • Modification of the crane will be done at the beginning of the Christmas shutdown (to agreed with the planning of the area) JL GRENARD EN-HE

  6. Vision system • Will used same equipment as used for HiRadMat • Regarding the return of experience at HiRadMat it make sense to install an optical fiber on the crane • Fix Cameras might be needed JL GRENARD EN-HE

  7. Radiation measurement mobile platform • Mostly finished some extra modifications need to be done (longer arm, flexible fitting for the probe, lighting)-> completely finished at the end of October JL GRENARD EN-HE

  8. Radiation measurement mobile platform JL GRENARD EN-HE

  9. Standard transport means • Repairs of the TA Boggies on going • A cleaning of the bottom of the shaft shall be done a lot of dust, concrete is on the floor JL GRENARD EN-HE

  10. Any questions? JL GRENARD EN-HE