LBT Q1 2007 Engineering Review Swing Arms (SWA) Gusick. Open Issues. Technical Swing arm shock absorber Schedule PF Swing Arm Commissioning Financial None Resource Telescope Time/Manpower – Telescope at horizon for ADSEC swing arm wiring and testing
E N D
Open Issues • Technical • Swing arm shock absorber • Schedule • PF Swing Arm Commissioning • Financial • None • Resource • Telescope Time/Manpower – Telescope at horizon for ADSEC swing arm wiring and testing • PF Swing Arm Commissioning – Rotator resource competition LBT Q1 2007 Engineering Review
Progress (Q1/2007) SX and DX ADSEC Swing Arms Installed ADSEC wiring, limit switch testing scheduled 2nd and 3rd week of April LBT Q1 2007 Engineering Review
Planning (Q2/2007) • ADSEC Swing Arm Preload • GUI Testing • Prime focus swing arm commissioning? LBT Q1 2007 Engineering Review
LBT Q1 2007 Engineering Review Swing Arms (SWA) Howard
Highlights (Q1/2007) • Installed right secondary swing arm in January • Installed left secondary swing arm in March LBT Q1 2007 Engineering Review
Open Issues • Technical • Repeatability measurement • Vibration measurement • Loose Brace on M3 Swing Arm on 3L • Schedule • Prime Focus Swing Arm Commissioning Plan • Swing Arm Shock Absorbers • Financial • None • Resource • Mountain manpower availability • Chamber lift shortage LBT Q1 2007 Engineering Review
Progress (Q1/2007) • Installed Secondary Swing Arms • Surveyed DX PF SA prior to LBC Red Installation • Wiring of Secondary Swing Arms in Progress LBT Q1 2007 Engineering Review
Planning (Q2/2007) • Come up with a Prime Focus SA Commisioning Plan • Repeatability • Vibration • Deploy/retract speed • AS Swing Arm Preload & Alignment • Primary Mirror Cover Test Fit #3 • Remove SX M3 SA (clean bearings while it is off) LBT Q1 2007 Engineering Review