1 / 5

PIP Update

PIP Update. Sept. 11 th 2013. Agenda. Summary Update Current Activities/Updates Recent PIP News Upcoming Talks, Reports, Meetings Updates/Talks: Mohamed Hassan - Booster Cavity Modeling and Proposed Measurements Dave Johnson - Laser Notcher Prototype & Status . Update. General Info

vida
Download Presentation

PIP Update

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. PIP Update Sept. 11th 2013

  2. Agenda • Summary Update • Current Activities/Updates • Recent PIP News • Upcoming Talks, Reports, Meetings Updates/Talks: • Mohamed Hassan - Booster Cavity Modeling and Proposed Measurements • Dave Johnson - Laser Notcher Prototype & Status

  3. Update General Info • PreAcc Beam: • Linac Beam: Probe? • Booster Beam: Tuning – beam for HEP • 10 turns -> MI • Studies still underway: • Transverse damper studies – not yet started – need to put system back together • Cogging software work continues – old system used in operation • Booster optics software – • Booster Longitudinal dampers –software effort just starting, new boards? • Booster RF cavity rework • Cavity from RF17 reinstalled yesterday – had a vacuum issue • Booster RF19 will be next – has been out of tunnel for some time to allow for extra cool down • RF8 was removed because of RF leakage (this was the first refurbished) • Spare Cavity Work – brazing plans? • Booster Ferrites • Were due 2nd or 3rd week of July – • Low Mu cores 60 on 8/23ship 9/11, 60 on 9/6 ship 9/18 and 76 (balance) on 9/27ship 10/3 • High mu cores – we are preparing a response before the next batch is made • HLRF – PO all signed off – but issues with purchasing agreement CPFF is causing issues!!! • Looking into an alternate SBK design • Linac Modulator - testing continues • Booster Shielding – work continues but issues regarding implementation • Short Kickers under test

  4. Recent PIP Budget/News • Supplemental Funding – approved and nearly spent There are several POs still needing to get finished • Budget Issues – Submitted FY14 labor and Budget • Labor plan is in place – entirely expect it to change • PIP 11 M FY14 budget uploaded • New director has not given any signal to PIP to slow down or change course • Labor Issues • We have not had the expected labor on a few parts of PIP • Cavity refurbishment is the most glaring shortfall • MSD techs have not become available • Looking into other options to move this process along • Please use the E-Log to put general work in progress updates/photos – weekly would be nice – if progress is being made in task • Need to post

  5. Upcoming Talks Sept 18: Dan Bollinger - Source Development Future Meetings to be Scheduled: • Kiyomi– Booster cogging plans • Eddy – Booster damper plans • Bill Pellico - Loss Scans and Shielding Assessment • Jon Reid - Solid State Installation - Final Report • Tan – RFQ Summary (after install of corrector and source B operating)

More Related