NA62 Organisation of the work - proposal PD/DT/PO-MH
NA62 – TC activities – Organisation of the work – proposals Integration team Integration team Experimental Area team Experimental Area team Sub-system teams Sub-system teams Design phase Installationphase PD/DT/PO-MH
NA62 – Integration team– Design phase • Tasks of the INTEGRATION team: • CATIA model and layoutdrawing of the NA62 experiment • Envelopemodels & Envelopedrawings of individualsub-detectors • Check and agreement with ‘Beatch files’ • AIM = All partnersworking to agreedlayout & dimensions • Manage change requests in an official/agreedway • Manage CDD/EDMS/CATIA CAD files • Check that the individual parts canbefixedtogether = no clashes • Check with the surroundingenvironment – cavern & services • Studiesof proximityservices routing, support structures, accessstructures (in collaboration with Experimental area team). • Installation studies PD/DT/PO-MH
NA62 – Experimental Area team– Design phase • Tasks of the EXPERIMENTAL AREA team: • Scheduling of the design and installation phases of the work • Liasonwith CERN groups for the provision of services: WATER, COOLING, GAS, VACUUM, VENTILATION, ELECTRICITY, CRYOGENICS, VACUUM, etc. Studies of external services routing by the CERN groups: support structures, access structures (in collaboration with Integration team). • Design of the Beamline /Liason with the machine • Study of the Beam dump. • Togetherwith the GLIMOS, the planning of the workincorporating the safety aspects and conformitywith CERN rules: work package descriptions, procedures, etc. • Arranging/Organising the removal of NA60 • Study of MNP33 Magnetdisplacement • TSO of Experimental area and buildings. PD/DT/PO-MH
NA62 – Sub-detector teams– Design phase • Tasks of the SUB-SYSTEMteams: • The conceptual and detailed design of the DELIVERABLES = SUB-SYSTEMS. In accordance with the agreedenvelopes (Integration team). • Managingenvelope changes in an agreedway (Change requestprocedure). • Working in accordance with the agreedschedule (Experimental Area team). • Workingtogetherwith the integration team for the exchange of CAD models, installation studies, cross-checks. • Detailedassembly and installation studies of the sub-detectors. PD/DT/PO-MH
NA62 – Integration team– Installation phase • Tasks of the INTEGRATION team: • Installation study cross-checks for the sub-systems • Detailed design, supply and installation of any missing parts (services, supports, etc) • Follow-up in the cavern of installation studies • Manage change requests in an official/agreed way • Manage CDD/EDMS/CATIA CAD files PD/DT/PO-MH
NA62 – Experimental Area team– Installation phase • Tasks of the EXPERIMENTAL AREA team: • Scheduling and progress tracking of the work • Installation of external services / Liason with the CERN groups for the installation of services: WATER, COOLING, GAS, VACUUM, VENTILATION, ELECTRICITY, CRYOGENICS, VACUUM….. • Together with the GLIMOS, the planning of the work incorporating the safety aspects and conformity with CERN rules: installation procedure descriptions (work package analysis WPA’s ), procedures, etc. The management of the WPA’s: documents, approval procedures, realisation. • Manage the installation of the experiment (together with the TC & GLIMOS) • MNP33 Magnet : displacement, integration & services • Manage the technical assistance (technicians, travelling crane operators, surveyors..) • Installation and the setting up of the beamline • Liason with the machine • Realisation of the beam dump • TSO of the Experimental Area and buildings. PD/DT/PO-MH
NA62 – Sub-detector teams– Installation phase • Tasks of the SUB-SYSTEMteams: • Working in accordance with the agreed schedule (Experimental Area team). • The writing of installation procedures (WPA’s) that describe: what work has to be executed, when it needs to be done, how it will be done (manpower and tooling), what safety measures will be taken, etc. • Interacting with the Experimental area team to prepare for, and obtain approval of, the installation procedures (WPA’s). • - All workers to attend CERN safety training courses (in order to obtain access, etc). • Providing the sub-detectors on the agreed dates and with the agreed means (manpower and tooling) to execute the work in accordance with the approved procedures. Respecting the safety rules. • Attendance at progress meetings. PD/DT/PO-MH