Review of MODAPS production activities including forward processing, PGE deliveries, baselining updates, and ongoing science testing for different collections. Notable mentions of Atmospheres, Land, Greenland, LANCE/GIBS, and assessment progress are highlighted.
E N D
MODAPS PIP Report June 20, 2017 1-844-467-4685 761062#
Summary of MODAPS Production 6/6 • Forward Processing (C6 Atmospheres, Land and Greenland IST) • Terra is at the leading edge, Aqua is two days behind due to a data outage on day 163.
Summary of PGE Deliveries to SDST 6/6 Collection 61 • Atmospheres: • We baselined a new version of PGE03 (6.1.1) on 6/13/17. • We baselined a new version of PGE06 (6.1.2) on 6/15/17. • We baselined a new version of PGE92 (6.1.0) on 6/16/17. • Atmospheres: • We baselined a new version of PGE04 (6.1.0) on 4/13/17. Collection 6 • Level 1: • We baselined a new version of PGE03 (6.0.50) on 6/20. • Atmospheres: • We baselined a new version of PGE04 (6.0.52) on 12/21. • Land: • We baselined a new version of PGE116 (6.0.58) on 5/30/17. • We baselined a new version of PGE147 (6.0.0) on 6/4/17. • We baselined a new version of PGE148 (6.0.0) on 6/4/17. • We baselined a new version of PGE149 (6.0.0) on 6/13/17. • We baselined a new version of PGE150 (6.0.0) on 6/13/17. • We baselined a new version of PGE113 (6.0.19) on 6/15/17 • LANCE/GIBS: • We baselined a new version of PGE137 (6.0.4) on 5/20/17.
Summary of Science Testing 6/16 • Atmospheres Science Testing: • A C61 Aqua 6 month test is running. 6/5/17 • Land Science Testing: • A C6 PGE116 v6.0.56 Terra and Aqua 16 day test is complete. 6/1/17 • A C6 PGE116N v6.0.56 Terra and Aqua 16 day test is complete. 6/1/17 • A C6 PGE26 v6.0.4 test is running. 6/5/17 • L1 Science Testing: