An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Bond Construction Update Citizens Oversight Committee Long Beach Community College District January 23, 2012 EDUCATE ENGAGE EMPOWER

  2. Agenda • Current Construction Projects • LAC Building A – Student Services Retrofit • LAC Building I (Bookstore) • LAC Master Landscape • LAC Stadium Parking Lot Lights and Veterans Stadium Lights • PCC MDAB (Multi-Disciplinary Academic Building) • PCC Building CC Retrofit • Upcoming Construction Projects • LAC Math Technology Building • PCC Building GG • LAC Building C Retrofit • Q & A

  3. Current Construction Projects LAC Building A – Student Services Retrofit Measure E 2008 • Considerable progress since last update • Exterior envelope & roof sheeting being installed • Structural walls on new addition in progress • End of construction anticipated Fall of 2012

  4. Current Construction Projects LAC Building I - Measure E 2008 • Building construction complete; casework in progress • Punch list items and fire alarm almost complete • Move in scheduled for February 2012

  5. Current Construction Projects LAC Building I - Measure E 2008 • Exterior landscape has started • Landscape includes privacy wall and dense planting • Project expected to be complete in March 2012

  6. Current Construction Projects LAC Master Landscape - Measure E 2008 • Phase 1, South of Bldg. A will bid Spring 2012 • Construction to start in Summer 2012 • Passive Storm water retention system • Low water use plants and trees • Pedestrian pathway alignment

  7. Current Construction Projects LAC Master Landscape - Measure E 2008 • Phase 2, North of Bldg A will bid Spring 2013 • Construction to start in summer 2013 • Active Storm water retention system • Low water use Plants and trees • Pedestrian pathway alignment

  8. Current Construction Projects Stadium Parking Lot Lights and Stadium Lighting Measure E 2008 • Stadium parking lot lights • Construction completed 1/6/2012 • All old fixtures removed, bases demoed and asphalt patched • Energy efficient lights and late night feature • Stadium lighting retrofit • Awaiting final DSA approval

  9. Current Construction Projects PCC MDAB (Multi-Disciplinary Academic Building) Measure E 2008 • MDAB building remodel project • Phase 1 of 2 currently under construction • Exterior envelope currently being constructed • Roof membrane 100% complete

  10. Current Construction Projects PCC MDAB (Multi-Disciplinary Academic Building) Measure E 2008 • Interior walls under construction • HVAC and mechanical being installed • Phase 1 Project to be completed Summer 2012

  11. Upcoming Construction Projects PCC Building CC Retrofit - Measure E 2008 • Building CC Fitness Center, offices and restrooms • Demolition and hazmat removal mostly complete • Duration of project approximately 12 months • Anticipated end of construction Fall 2012

  12. Upcoming Construction Projects Will house Math and Culinary Arts instructional program as well as Reprographics Design Build delivery method Final 3 Qualified Design Build Entities (DBE) selected Design proposals from 3 DBE’s received and are currently being reviewed Anticipate awarding at the February Board meeting Anticipated start of construction 2013 LAC Math Technology Building – Measure E 2008

  13. Upcoming Construction Projects PCC Building GG - Measure E 2008 • Design Build delivery method • Request for Qualifications (RFQ) have been received and under review • 16 Design Build Entities (DBE) submitted qualifications • Building to house Health Services, EOPS, DSPS, Financial Aid, Cashier, A&R, and Counseling • Estimated start of construction December 2013

  14. Upcoming Construction Projects LAC Building C Retrofit - Measure E 2008 • Hired Architect to do design work • Program phase is currently ongoing • Work includes modernization of structure, classrooms spaces, and office areas

  15. Liberal Arts Campus Site Plan l i b e r a l a r t s

  16. Pacific Coast Campus Site Plan p a c i f i c c o a s t

  17. QUESTIONS& ANSWERS EDUCATE ENGAGE EMPOWER